We are now moving quickly through the build and getting block walls up on Terrace Lots 11-14.
· We expect to begin pouring slabs in the next two weeks for Terrace Lots 15-16.
· First floor framing for Lots 1-8 is almost completed. Ground floor framing for Lots 11-14 will start next week.
· Roofing will start to be installed over the coming weeks.
· Expected settlement Lots 1-18: Q1 2023.
· Expected settlement Lots 19-30: Q1 2023.
May 2022
We are now moving quickly through the build and getting roofs up on Terrace Lots 11-14.
· We expect to begin pouring slabs next week for Terrace Lots 15-20.
· First floor framing for Lots 11 – 14 is almost completed. Ground floor framing for Lots 11-14 has been finished.
· We have started ground works for the Residences including moving the electric power mains underground.
· Expected settlement Lots 1-18: Q1 2023.
· Expected settlement Lots 19-30: Q1 2023.
Expected settlement Lots 50-57: Q1 2023.