Nuovo Construction Update Centre

Beginning of October 2021

  • Site works have now commenced in line with schedule.
  • We have begun clearing the site. This process will take 3 weeks.
  • Estimated settlement time remains at Q4 2022.

 

Mid-October 2021

  • Almost finished clearning and then we will have 3 weeks of fill coming to site (truck every 6 mins for 3 weeks).
  • We are now sold out of Stage 1.
  • We will start laying slabs during the middle of December 2021.
  • Expected settlement is Q4 2022.

November 2021

  • We have finished clearing the site.
  • We have started to bring fill onto the site.
  • Retaining being done as we go.
  • We will start laying slabs during the middle of December 2021.
  • Expected settlement is Q4 2022.

December 2021

  • We will continue to bring fill onto the site.
  • Even with the rain we haven’t lost too much time.
  • Retaining will be done as we go.
  • We will start laying slabs in early January 2022.
  • Expected settlement is Q4 2022.

January 2022

  • We are now retaining and laying the footings and piers in preparation for the slabs to be poured.
  • We have lost some time with rain delays which we will try to get back in the coming months.
  • Retaining will be done as we go.
  • We will start laying slabs mid-February 2022.
  • Expected settlement is Q4 2022.

March 2022

  • We are now moving quickly through the build and getting walls up on Terrace Lots 1-8.
  • We expect to begin pouring slabs in the next two weeks for Terrace Lots 10-18.
  • By the end of next month we will have begun work on the Residences as retaining will be completed.
  • We lost some time due to the floods in February.
  • Expected settlement is now Q1 2023.

April 2022

  •        We are now moving quickly through the build and getting block walls up on Terrace Lots 11-14.

    ·       We expect to begin pouring slabs in the next two weeks for Terrace Lots 15-16.

    ·       First floor framing for Lots 1-8 is almost completed. Ground floor framing for Lots 11-14 will start next week.

    ·       Roofing will start to be installed over the coming weeks.

    ·       Expected settlement Lots 1-18: Q1 2023.

    ·       Expected settlement Lots 19-30: Q1 2023.

May 2022

  •        We are now moving quickly through the build and getting roofs up on Terrace Lots 11-14.

    ·       We expect to begin pouring slabs next week for Terrace Lots 15-20.

    ·       First floor framing for Lots 11 – 14 is almost completed. Ground floor framing for Lots 11-14 has been finished.

    ·       We have started ground works for the Residences including moving the electric power mains underground.

    ·       Expected settlement Lots 1-18: Q1 2023.

    ·       Expected settlement Lots 19-30: Q1 2023.

  •            Expected settlement Lots 50-57: Q1 2023.

June 2022

  • In the next week we will get the roofs up on Terrace Lots 15-16.
  • First floor framing for Lots 15 – 16 is almost complete. Ground floor framing for Lots 15 -16 has been finished.
  • We have started brickworks and cladding on Lots 1-8.
  • Flooring is expected in Lots 1 – 8 at the end of the month.
  • Expected settlement Lots 1-18: Q1 2023.
  • Expected settlement Lots 19-30: Q1 2023.
  • We have started ground works for the Residences including moving the electric power mains underground.
  • We expect to begin pouring slabs this weekend for Terrace Lots 17-20.
  • Expected settlement Lots 50-57: Q1 2023.

July 2022

  • In the next week we will get the roofs up on Terrace Lots 17-20.
  • First floor framing for Lots 17 – 18 is almost complete. Ground floor framing for Lots 21-22 will be finished shortly.
  • We have started brickworks and cladding on Lots 1-8.
  • Flooring is expected in Lots 1 – 8 at the end of the month.
  • Expected settlement Lots 1-18: Q1 2023.
  • Expected settlement Lots 19-20: Q1 2023.
  • We have started ground works for the Residences.
  • We expect to begin pouring slabs for the Residences this month.
  • Expected settlement Lots 50-57: Q1 2023.
Privacy Settings
We use cookies to enhance your experience while using our website. If you are using our Services via a browser you can restrict, block or remove cookies through your web browser settings. We also use content and scripts from third parties that may use tracking technologies. You can selectively provide your consent below to allow such third party embeds. For complete information about the cookies we use, data we collect and how we process them, please check our Privacy Policy
Youtube
Consent to display content from Youtube
Vimeo
Consent to display content from Vimeo
Google Maps
Consent to display content from Google
Spotify
Consent to display content from Spotify
Sound Cloud
Consent to display content from Sound

Copyright 2022 @ JAM Group